Project Portfolio - Hilton Garden Inn , Southpoint – Durham, NC
The six-story Hilton Garden Inn was originally designed with concrete block as the
axial load bearing wall material. The change to SigmaStud® delivered
exceptional value to the construction team, with the component weight of SigmaStud®
(8psf) replacing the much more cumbersome 45psf concrete material. This 80% reduction
in bearing weight resulted in the utilization of a traditional thickened slab in
place of a larger, thicker foundation. Additionally, the decrease in the wall mass
also produced a lower base shear, minimizing materials needed for shear wall construction.
As a result of the change to SigmaStud® and by combining it with
TSN’s StiffWall® to address shear forces, the structural components
were erected in six weeks rather than the 3.5 months it normally would have taken
with the concrete block material.
|