SUBSTITUTION
REQUEST
(After the Bidding phase) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Undersigned certifies:
- Proposed substitution has been fully investigated and determined to be equal or
superior in all respects to specified product.
- Same warranty will be furnished for proposed substitution as for specified product.
- Same maintenance service and source of replacement parts, as applicable, is available.
- Proposed substitution will have no adverse effect on other trades and will not affect
or delay progress schedule.
- Cost data as stated above is complete. Claims for additional costs related to accepted
substitution which may subsequently become apparent are to be waived.
- Proposed substitution does not affect dimensions and functional clearances.
- Payment will be made for changes to building design, including A/E design, detailing,
and construction costs caused by the substitution.
- Coordination, installation, and changes in the Work as necessary for accepted substitution
will be complete in all respects.
|
|
|
|
Submitted by:
|
|
|
Signed by:
|
|
|
Firm: |
|
|
Address |
|
|
Telephone: |
|
|
Attachments: |
|
|
|
|
A/E's REVIEW AND ACTION
|
|
Substitution approved - Make submittals in accordance with Specification Section
01330. |
|
Substitution approved as noted - Make submittals in accordance with Specification
Section 01330.
|
|
Substitution rejected - Use specified materials.
|
|
Substitution Request received too late - Use specified materials.
|
|
|
|
|
|
|
Copyright 1996, Construction Specifications Institute,
99 Canal Center Plaza, Suite 300 Alexandria, VA 22314
|
September 1996
CSI Form 12.1A |
|
|
|